P1.2216 billion projects for 2026 implemented
BAGUIO CITY, Philippines – Mayor Benjamin Magalong has unveiled the major infrastructure and tourism development projects in Baguio City for 2027 with a proposed funding of P1,690,235,000 to be drawn from national government allocations.
“We have worked hard on these projects to improve public facilities, mobility, disaster preparedness and tourism infrastructure,” Magalong said.
The Local Finance Committee said the projects were proposed under the Department of Public Works and Highways (DPWH) and were included in the 2027 National Expenditure Program (NEP) formulated by Magalong.
It was clarified that the inclusion of DPWH projects in the 2027 NEP is part of the proposed budget of the national government and remains subject to the budget approval and implementation process.
Among the major projects is the P225 million rehabilitation of the Maharlika Livelihood Complex.
Other major projects are the P62 million construction of a multi-purpose building and barangay hall in Holy Ghost Extension; P63.25 million for a multi-purpose building with roof deck and slope protection in Barangay San Vicente; and P46 million for the completion of an evacuation center in Barangay City Camp Proper.
The proposed infrastructure program also includes sidewalk improvements on various roads in the city, including Asin Road, Manuel Roxas Road, Rimando-Ambiong Road, Military Cut-off Road, Session Road, South Drive, Gov. Pack Road, Leonard Wood Road, Kisad Road, Gen. Luna Road and Harrison Road with a total cost of P153,210,000.
Additional projects in the barangay are also set, including the completion or construction of multi-purpose halls and buildings in Balsigan, City Camp Central, Gabriela Silang, Camdas, Imelda R. Marcos and Lourdes Subdivision Proper, as well as the construction of a road in Modern Site West.
According to Magalong, the Tourism Infrastructure and Enterprise Zone Authority (TIEZA) is also expected to support three major projects, the proposed P500 million grant for a sewerage treatment plant, P150 million for the rehabilitation of Session Road and P400 million for the second phase of the rehabilitation of Burnham Park.
He said the city government will continue to seek funding support from national government agencies and other institutions to advance priority projects that will benefit the city.
P1.2216 billion projects for 2026 implemented
According to the Local Finance Committee, the city government’s infrastructure and non-infrastructure projects being implemented this year amounted to approximately P1.2216 billion for 2026.
In the report, the finance body said that a total of P704.7 million came from internal sources of funds or local government resources.
The local funds were supplemented by external funds totaling P516.9 million, mostly assistance from national government agencies including the Local Government Support Fund (LGSF), Philippine Sports Commission (PSC), Dangerous Drugs Board (DDB), Philippine Amusement and Gaming Corporation (PAGCOR) and Department of Transportation (DOTr), a product of Mayor Magalong’s fundraising efforts.
According to the report, the P704.7 million was allocated for 124 infrastructure projects. Of the 124 locally funded infrastructure projects, 93 are covered by the annual budget worth P412.7 million, while 31 projects worth P292 million are funded through supplemental budgets.
Under the annual budget, 57 projects worth P202.2 million, or 62 percent, have been completed.
Another 17 projects worth P115.2 million are ongoing, six projects worth P44.9 million are under procurement and 13 projects worth P50.4 million are still preparing their respective programs of work (POW).
For the supplemental budget, 13 projects worth P23.8 million, or 42 percent, have been completed.
Eight projects worth P154.5 million are ongoing, two projects worth P19 million are under procurement, while eight projects worth P94.7 million are still in the POW preparation stage.
The bulk of the P516.9 million from external funding sources came from the LGSF.
Among the major projects supported by this fund are the rehabilitation of the Maharlika Livelihood Center and the Baguio Convention Center, both with an allocation of P100 million each; the P90 million rainwater harvesting facility at Camp 8 Watershed; and the rehabilitation of the Burnham Park Skating Rink and the improvement of the swimming pool at the Athletic Bowl, with an allocation of P30 million and P40 million, respectively.
Also included are the P30-million rehabilitation of the Baguio Museum and the P12.9-million rehabilitation of Emilio Aguinaldo Park Phase 2 under the Green Green Program.
The LGSF also allocated P56 million for the Rice Subsidy Program, which has already been implemented through the distribution of assistance to vulnerable sectors.
Other externally funded projects are the P20-million provision of equipment to the Athletes’ Quarters through the PSC, the P5-million rehabilitation of the fourth floor of the Mines View Building for the Balai Silangan program through the Dangerous Drugs Board and P13 million from PAGCOR for the rehabilitation of the Upper Quezon Senior Citizen Center, renovation of the Pinsao Proper Barangay Hall, and rehabilitation of the Fort Del Pilar Gym.
The DOTr also allocated P20 million for the Emergency Transport Support Program, an initiative of the City Administrator’s Office that aims to provide support to public utility vehicle operators.
According to Magalong, these projects are in various stages of implementation, including the preparation of the program of works, procurement, bidding, contract award and actual implementation.
He said these investments are expected to improve public facilities, strengthen basic services, support vulnerable sectors and provide better infrastructure and services for residents.
He added that the city will continue to strive to complete locally and externally funded projects. The city will also continue to leverage assistance from national government agencies to support its development priorities.